Understanding the concept of Float and Float Ownership is critical to those administering NEC3 Engineering and Construction Contract. Unfortunately both concepts are often misunderstood. I have heard the phrase “Contractor owns the float” too many times. Let’s look into this in more detail.
Society of Construction Law Delay and Disruption Protocol describes Float (sometimes also called Slack) as “the amount of time by which an activity or group of activities may be shifted in time without causing delay to completion”. Float is calculated by subtracting the time necessary to perform a task from the time available to perform it. There are a few types of float or float related concepts recognised under NEC3.
- Free Float is the amount of time an activity can be delayed beyond its early start/early finish dates without delaying the early start or early finish of any immediately following activity
- Time Risk Allowance is is the amount of time allowed by the contractor in programming activities to allow for the risk of delay should problems arise.
- Total Float is the amount of time that an activity may be delayed beyond its early start/early finish dates without delaying the contract completion date.
- Terminal Float is the period between Planned Completion and Completion date set in the contract.
- Negative Float is a programming concept, the manifestation of which is Delay. Negative Float is an expression used to describe the time by which the duration of an activity or path has to be reduced in order to permit an imposed date to be achieved. Negative float only occurs when an activity on the critical path is behind Programme. If you look at the Total Float column in your Programme and see -20d, it means that there is 20d negative float in the Programme, therefore you are at risk of delaying the completion by 20 working days.
NEC3 defines float ownership as follows:
- Time Risk Allowance is owned by the Contractor. It cannot be used to mitigate the effect of a compensation event. It is protected in the same way as Terminal Float.
- Total Float is available to both the Employer and the Contractor on first come first served basis. It can be used to mitigate delays caused by compensation events.
- Terminal Float is owned by the Contractor. It cannot be used to mitigate the effect of a compensation event.
Now that we have settled the basic definitions let’s look into few areas of concern that I have noticed coming up every now and then.
Is it necessary to show the Time Risk Allowance in the Programme under NEC3?
NEC3 Clause 31.2 is clear that the Contractor shows on each Programme which he submits for acceptance provisions for Float and Time Risk Allowances. Both should be also assessed with every revision of the Programme and any significant erosion of Float or visible Negative Float should be clearly explained in the Programme Narrative. Remember that accounting for Time Risk Allowance gives the Project Manager the reassurance that the risks for each activity have been considered.
Lack of Time Risk Allowance in the Programme is a valid reason to reject the Programme.
Why is it critical to understand the types of float and their ownership?
Float is a fluid concept.
Free Float and Total Float are recalculated every time the Programme is scheduled and therefore change with every iteration of the Programme. That’s where it becomes tricky for the Contractor as well. If the Contractor fails to recognise activity float as Time Risk Allowance he risks it being used up by events for which he is not responsible. Time Risk Allowance should be protected in the same way as Terminal Float.
Is Time Risk Allowance “lost” if not used on an activity or can it be carried over?
Clause 32.1 requires the actual progress achieved on each operation and its effect upon the timing of the remaining work to be shown in the revised Programme. If a task finishes without using its Time Risk Allowance and another task can start without disruption then the answer is yes. Any unused TRA from activities which are not on the critical path will appear as float and then become available to who ever (Contractor or Employer) gets there first.
Interestingly if Time Risk Allowance is not used and the Programme is rescheduled this may result in Planned Completion shifting to an earlier date, which brings me to the next question.
What happens to Terminal Float if Planned Completion shifts to an earlier date?
If Planned Completion moves forward due to unused risk allowance and the gap between the Planned Completion and Contract Completion becomes greater, this can be “banked” as Terminal Float. It is a common misconception that once the programme is baselined, the terminal float is set in stone until such time that the Contractor decides to use it.
Finally, can the Terminal Float be reduced by the Project Manager?
If the Project Manager wants to reduce the Terminal Float, he can instruct the Contractor to provide quotation for acceleration. This is done via mechanism described in Clause 36 – Acceleration.
Have you had any interesting arguments about float in your organisation? Perhaps there is a float-related issue that you’re not sure how to deal with? Let’s have a chat in the comments section or in person.
Best, Radek Makar Planning Director | ViViAD radek@viviad.co.uk |
We are a London based, independent construction consultancy specialising in Project Services with Dispute Resolution Reachback. We act as interim managers but are open to longer commissions.
Our offer includes Planning Management, Commercial Management, Risk Management, Claims Management, Dispute Services, NEC Advice and Training.